Removal of external scaffolding 40% completed
Construction of the internal walls Started, 20% completed
Construction and installation of the sewage system, completed 80%
Luxury floor laying, gress wood texture and marble, 90% completed
Related articles
Window and Balustrade installation, Tower one
The external structure is complete.
Outdoor painting 100% completed
Windows installed 100% completed
Glass parapets installed 100% completed
removal of external scaffolding Started
Started luxury floor laying, gress wood texture and marble, 30% completed
Related articles
Luxury flooring, Italian porcelain stoneware
The first phase of the project includes the completion of the entire Residential area. This includes the Sail Palace, three luxurious and exclusive residential towers and all associated service facilities, the sports center with gyms, the wellness center, and bars. The private parking lots and the surrounding garden park will be constructed during this stage.
The external structure of the towers ended at 80%, external painting complete 60%, windows and parapets 80% complete